Zweck
Gjøvik municipality is the contracting authority for the procurement. Procurements- the joint unit in the Gjøvik region is holding the competition on behalf of the contracting authority. Gjøvik municipality shall establish a fully fledged backup water system that shall strengthen security of supply for Biri and Gjøvik. A new water treatment facility shall be established at Biri as a part of the project. The contract is for engineering design services for and the erection of the water treatment facility. The contract will be carried out as a turnkey contract in accordance with NS 8407 and includes, among other things, the establishment of a construction pit with sheet piling and foundations, process basements and waterproof basins, process hall, technical rooms, administration areas, technical installations within HVAC and electro as well as the accompanying outdoor work. The contract has interface with other contracts for machine and process equipment, automation, raw water pump station and pipeline installations. The contracts for machinery and process equipment and automation can be transferred to the turnkey contractor. The procurement ́s estimated value is approx. NOK 180 million excluding VAT.
Lose 1 Los
BA-26-024-GK Project reserve water Gjøvik-Biri ENT1A1 Water treatment plant ground and construction work.
Gjøvik municipality is the contracting authority for the procurement. Procurements- the joint unit in the Gjøvik region is holding the competition on behalf of the contracting authority. Gjøvik municipality shall establish a fully fledged backup water system that shall strengthen security of supply for Biri and Gjøvik. A new water treatment facility shall be established at Biri as a part of the project. The contract is for engineering design services for and the erection of the water treatment facility. The contract will be carried out as a turnkey contract in accordance with NS 8407 and includes, among other things, the establishment of a construction pit with sheet piling and foundations, process basements and waterproof basins, process hall, technical rooms, administration areas, technical installations within HVAC and electro as well as the accompanying outdoor work. The contract has interface with other contracts for machine and process equipment, automation, raw water pump station and pipeline installations. The contracts for machinery and process equipment and automation can be transferred to the turnkey contractor. The procurement ́s estimated value is approx. NOK 180 million excluding VAT.
- CPV-Code
- 45252120
Eignungskriterien 6 Einträge
Eintragung in ein Handelsregister
Tenderers are required to have a legally established company. Documentation requirements: * Norwegian companies: Company Registration Certificate * Foreign companies: Proof that the company is registered in a trade or business register as prescribed by the law of the country where the tenderer is established.
Losbezug: LOT-0001
Sonstige wirtschaftliche oder finanzielle Anforderungen
Tenderers must have sufficient financial capacity to carry out the assignment. Documentation requirements: · Annual accounts for 2024 and 2025, auditor approved. · Credit rating based on the most recent financial figures. The rating shall be carried out by a credit rating company with a licence to conduct this service and it must not be older than 6 months calculated from the deadline for submitting a request for participation in the competition. The contracting authority reserves the right to carry out their own credit assessments in an independent company. If a tenderer has a justifiable reason for not submitting the documentation required by the contracting authority, he can document his economic and financial capacity by presenting any other document that the Contracting Authority deems appropriate. If a tenderer is in doubt, it is recommended to contact the contracting authority and ask questions about the type of documentation this can be.
Losbezug: LOT-0001
Referenzen über vergleichbare Dienstleistungen
Tenderers shall have sufficient relevant experience. Documentation requirements: An account shall be provided of relevant reference projects carried out in the last 10 years. A total of four (4) reference projects can be referenced. The following information must be given on each of the projects: · Assignment and Project Description · The contracting authority and gender neutral preferred, including contact information. · Duration of the contract that the tenderer has carried out. · The value of the contract that the tenderer has carried out The account shall be given on the form for reference projects, Annex C. The tenderer is required, through a description of reference projects, to identify the relevance for the assignment. Tenderers can document their experience by referring to competence of the personnel he has at his disposal and can use this assignment, even if the experience has been gained while the personnel have served another employer/business. Note that the same reference projects are used to possibly opt out of any redundant, qualified tenderers, cf. point 3.9 below. (CVs for this description shall not be enclosed.)
Losbezug: LOT-0001
Bescheinigungen von Qualitätskontrollinstituten
Tenderers shall have a suitable and implemented quality assurance system. The requirement must be fulfilled by the tenderer himself. Documentation requirements: An account of the tenderer ́s quality assurance system as well as a copy of the table of contents. The account shall have a maximum of three A4 pages with the following formatting: · Margin: 2.5 cm · Font: Arial (Body) font size 11 · Line spacing 1.5 If a tenderer is certified in accordance with ISO9001 or equivalent certification schemes, it will be sufficient to fulfil the requirement.
Losbezug: LOT-0001
Umweltmanagementnachweise unabhängiger Stellen
The tenderer shall have a suitable and implemented environmental management system. The requirement must be fulfilled by the tenderer himself. Documentation requirements: An account of the tenderer ́s environmental management system as well as a copy of the table of contents. The account shall have a maximum of three A4 pages with the following formatting: · Margin: 2.5 cm · Font: Arial (Body) font size 11 · Line spacing 1.5 If the tenderer is certified in accordance with ISO 14001:2015, Miljøfyrtårn , EMAS or equivalent certification schemes, this will be sufficient to fulfil the requirement.
Losbezug: LOT-0001
Ausbildungs- und Berufsqualifikationen
Technical and professional competence and relevant experience is required of the following key personnel who shall be used for this assignment: · Project Manager · Engineering design group manager · Site Manager Documentation requirements: CVs for offered key personnel, which i.a. ought to include: · education, · professional experience, · relevant courses, · a description of the up to three most relevant reference projects for each offered key personnel. The tenderer is required to use the template for CVs to present relevant competence and experience. The contracting authority can, if needed, choose to contact the references. Only the offered key personnel ́ documented competence and experience shall be included in the evaluation according to this criteria. The tenderer ́s general references (submitted for qualification) will not be emphasised here. Annex E, template for the CV shall be used for the response to this criteria. Note that the same CVs will be used to possibly opt out of any redundant, qualified tenderers, cf. point 3.9 below.
Losbezug: LOT-0001
Zuschlagskriterien 3 Einträge
Preis
55 %Price
Losbezug: LOT-0001
Qualität
30 %Climate and environment
Losbezug: LOT-0001
Qualität
15 %Implementation plan
Losbezug: LOT-0001
Ausschlussgründe 26 Einträge
Ausschlussgrund
Is the tenderer in a bankruptcy situation? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers in such a situation is obligatory in accordance with the current national law with no exceptions, when the tenderer is still able to carry out the contract.
Ausschlussgrund
Is the tenderer in a bankruptcy situation? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers in such a situation is obligatory in accordance with the current national law with no exceptions, when the tenderer is still able to carry out the contract.
Ausschlussgrund
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies, by enforceable judgement been convicted of corruption by a verdict handed down not more than five years ago, or a rejection period determined directly in the judgement that still applies? Corruption as defined in Article 3 of the Convention on Combating Corruption, involving European Communities or European Union member states (EUT C 195 of 25.6.1997, s. 1), and in Article 2, point 1, in the Council ́s framework decision 2003/568/RIA of 22 July 2003 on combating corruption in the private sector (EUT L 192 of 31.7.2003, p. 54). This rejection reason also includes corruption as defined in national law for the contracting authority or supplier.
Ausschlussgrund
Is the supplier in a situation where he has been forced debt arrangement? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers in such a situation is obligatory in accordance with the current national law with no exceptions, when the tenderer is still able to carry out the contract.
Ausschlussgrund
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies, at the time a legally convicted verdict of participation in a criminal organisation by a verdict handed down no more than five years ago, or a rejection period set out directly in the judgement that still applies? Participation in a criminal organisation as defined in Article 2 of the Council ́s framework decision 2008/841/RIA of 24 October 2008 on control of organised crime (EUT L 300 of 11.11.2008, p. 42).
Ausschlussgrund
Has the tenderer entered into agreement(s) with other tenderers with the intention of turning the competition?
Ausschlussgrund
Is the tenderer aware of breaches of environmental provisions as stated in national law, the relevant notice or procurement documents or Article 18 (2) of Directive 2014/24/EU.
Ausschlussgrund
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies, in the event a legal verdict has been convicted of money laundering or financing terrorism by a verdict handed down no more than five years ago, or a rejection period set out directly in the judgement that still applies? Money laundering or financing terrorism As defined in Article 1 of the European Parliament and Council Directive 2005/60/EF of 26 October 2005 on preventive measures against the use of the financial system for money laundering and financing terrorism (EUT L 309 of 25.11.2005, p. 15).
Ausschlussgrund
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies, at the time a legally convicted of fraud has been convicted of fraud by a verdict handed down not more than five years ago, or a rejection period determined directly in the judgement that still applies? Fraud included in Article 1 of the Convention on protection of the Financial Interests of the European Communities (EFT C 316 of 27.11.1995, p. 48).
Ausschlussgrund
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body or has the competence to represent or control or make decisions in such bodies, in the event a legal verdict has been convicted of child labour and other forms of human trafficking by a verdict handed down no more than five years ago, or a rejection period determined directly in the judgement that still applies? Child labour and other forms of human trafficking as defined in Article 2 of the European Parliament and council directive 2011/36/EU of 5. 1 April 2011 on the prevention and control of human trafficking and the protection of its victims and for compensation of the Council ́s framework decision 2002/629/RIA (EUT L 101 of 15.4.2011, p. 1).
Ausschlussgrund
Is the tenderer in an insolvency situation? Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers in such a situation is obligatory in accordance with the current national law with no exceptions, when the tenderer is still able to carry out the contract.
Ausschlussgrund
Is the tenderer aware of breaches of provisions on working conditions as stated in national law, the relevant notice or procurement documents or Article 18 (2) of Directive 2014/24/EU.
Ausschlussgrund
Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers in such a situation is obligatory in accordance with the current national law with no exceptions, when the tenderer is still able to carry out the contract.
Ausschlussgrund
Has the tenderer: a) given grossly incorrect information with the notification of the information required to verify that there is no basis for rejection, or of the qualification requirements being fulfilled, b) failed to provide such information, c) made reservations immediately to present the supporting documents requested by the contracting authority, or d) improperly affected the contracting authority ́s decision process to acquire confidential information that could give this an unlawful advantage in connection with competition, or negligently has given misleading information that can have a significant influence on decisions on rejection, selection or award?
Ausschlussgrund
Is the tenderer aware of a conflict of interest as stated in national law, the relevant notice or procurement documents?
Ausschlussgrund
Has the tenderer or an entity associated with the supplier advised the contracting authority or in another way been involved in the planning of the competition?
Ausschlussgrund
Has the tenderer committed serious errors in professional practice? If relevant, see the definitions in national law, the relevant notice or procurement documents.
Ausschlussgrund
Has the tenderer committed significant breaches of contract in connection with the fulfilment of a previous public contract, a previous contract with a public contracting authority or a previous concession contract, where the breach has led to the cancellation of the contract, compensation or other similar sanctions?
Ausschlussgrund
Is the tenderer aware of breaches of provisions on social conditions as stated in national law, the relevant notice or procurement documents or Article 18 (2) of Directive 2014/24/EU.
Ausschlussgrund
Have tenderers failed to fulfil all their social security obligations in the country where they are established and in their member state, if this is a different country than what he is established in?
Ausschlussgrund
Specify why, under the mentioned circumstances, one is able to carry out the contract, considering the current national provisions and measures for continuing the business activities? It is not necessary to provide this information if rejection of tenderers in such a situation is obligatory in accordance with the current national law with no exceptions, when the tenderer is still able to carry out the contract.
Ausschlussgrund
Has the tenderer not fulfilled all of his tax and duty obligations in both the country where he is established and in the contracting authority's member state, if this is a different country than what he is established in?
Ausschlussgrund
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body, or has the competence to represent or control or make decisions in such bodies, in the event a legal verdict has been convicted of acts of terrorism or criminal acts connected to terrorist activities by a verdict handed down no more than five years ago, or a rejection period set directly in the judgement that still applies? Acts of terrorism or criminal acts relating to terrorist activity as defined in Article 1 and 3 of the Council ́s framework decision 2002/475/RIA of 13 June 2002 on combating terrorism (EFT L 164, af 22.6.2002, p. 3). This rejection reason also includes incitement to, participation or attempts to commit such actions as included in Article 4 in the mentioned framework decision.
Ausschlussgrund
Is the tenderer himself or a person, who is a member of the tenderer's administration, management or supervisory body, or has the competence to represent or control or make decisions in such bodies, have been legally convicted of offences regarding professional behaviour in defence procurements?
Ausschlussgrund
Is the tenderer assessed to lack the reliability necessary to exclude the risk of national security?
Ausschlussgrund
The contracting authority shall state that in Norway there are national rejection reasons. These shall be described in the procurement documents. Tenderers must respond to whether they are in one or more of the situations described in the national rejection reasons.